top of page

CASE STUDIES

BCD/19/00279/FP

​

Building Control application and working drawings for a domestic property in Brixworth, Northampton. 

This is an ongoing self build kitchen extension which is built in the most sustainable way. Renewable materials such as structurally graded timber and recycled roofing tiles along with HUGE insulation values make this a very cost effective build both in build cost and running costs. This extension is almost twice as efficient when compared to a standard domestic build. Due to the Covid-19 pandemic this build project is on hold due to material limitations however finished images will be posted soon.

P18/S0446/FUL

​

To erect a single storey, timber, modular building of 120m2 to be used for a 4 berth holiday let.

​

This building was designed and spec'd by ourselves with planning permission granted.

Extremely eco-friendly with high insulation values this modern building has low running costs and a high end finish. 

​

From design to completion on this project was 20 weeks. 12 weeks for planning permission and 8 weeks construction. The construction was undertaken buy a local company called The New Factory who we work extremely close with who build in factory and deliver to site to decrease disruption and time spent on site

​

N/2019/1342

​

Change of Use Application - Conversion of a former Buddies USA Diner in Kingsthorpe, Northampton to a new gastro pub to be called The Olde Cobbler. 

 

This planning application was approved on the 19th of February 2020 and consisted of many internal changes both structural and non structural, exterior additions and interior design.

For this Project we also submitted and had approved an advertisement consent application.

​

 N/2020/0170

​

Installation of a silo for the storage of plastic granules used in the manufacturing of automotive components. Northampton - GROUPE PLASTIVALOIRE

​

DESIGN ONLY PROJECT

​

For this project the local authority would not grant planning permission for a new build on the site.

​

The solution was to build a barn which would be used as agricultural for 3 years and then later apply for change of use.

​

This barn was to be built with suitable foundations and structural elements so that it would simply be a matter of resuming the building process to transform a barn into a small home.  The build was split into individual components and panels which could be re-arranged very easily and/or swapped to glazed panels etc...

​